Views: 0 Author: ECHELON Publish Time: 2026-10-30 Origin: Site
A European resort operator runs 60 electric golf carts across two 18-hole courses, charging overnight in an open-sided barn. During peak season, eight to ten carts per week were not fully charged by the 6 a.m. start, and the operator was preparing to replace all 60 chargers.
The chargers were not failing. They were finishing too late.
We logged charging start times, starting state of charge and completion times for two weeks.
Charging typically began at 11 p.m. when the barn was locked, which gave a seven-hour window. A 72 V / 100 Ah pack with a 3.3 kW charger needs roughly six hours from 20 percent, but only if it actually starts at 20 percent. Carts returning at 10 to 15 percent needed more, and cold autumn mornings added further time on top.
The problem was sizing against the pack rather than against the window. And only the busiest carts were actually affected.
1. Rather than replacing all 60 chargers, we identified the 20 carts with the heaviest daily use.
2. Moved those to 6.6 kW OBC units (PO-AB-6G series), cutting their charging time to about three hours.
3. Left the remaining 40 carts on their existing 3.3 kW units.
4. Added a staggered start schedule so the barn supply was not loaded simultaneously.
Morning readiness went from roughly 85 percent to 100 percent. Twenty chargers were replaced instead of the proposed 60, at roughly one third of the planned cost. Peak electrical demand stayed unchanged because the start times were staggered rather than simultaneous.
"We were about to buy 60 chargers. We needed 20." — Operations director
Tell us fleet size, pack voltage and capacity, and the hours actually available for charging. We will model the charging window before quoting anything, because in a fleet the correct charger is decided by the schedule rather than by the pack label.